Barbeth

  • Scheme Size: 100kW
  • Gross Head: 105m
  • Design Flow: 132 l/s
  • Turbine Type: Turgo
  • Pipe: 400mm PE100 (1512m)
  • Estimated Generation: 364,000kWH
  • Location: Dumfries and Galloway
  • Status of Site: The scheme was commissioned in August 2016. Construction started at the beginning of April 2016 and was finished by the end of August 2016.